Change of property use. Building is being rebuilt into 10 apartments.
Finalization date 2023-11-15
Building 843 m2
On completion 10 apartments
Bank – BBVA
200 000 euro with 5% return of investment – CLOSED
225 000 euro per apartment – CLOSED
2023-07-01
Roof top work and facade initiated
2023-06-10
All apartments finalized
2022-10-05
Rehabilitation work start
2022-05-15
Capital investments for start completed
2022-03-10
Presentation of Vista Playa No 6 to investors
Living room in one of Vista Playa No 6 apartments after staging process.